Route 1A’s $20.3 Million Seawall Grant Covers Three of 14 Sections. The State’s 2021 Estimate for the Rest: $58 Million.

Salt marsh at Odiorne Point, Rye. Photo: Carol M. Highsmith, Library of Congress.
Independent New Hampshire Journalism · Northfield, NH
Seacoast · Infrastructure
Route 1A’s $20.3 Million Seawall Grant Covers Three of 14 Sections. The State’s 2021 Estimate for the Rest: $58 Million.

The Fiscal Committee accepted the federal money on Nov. 20, 2026. The Department of Transportation’s own grant application shows what it buys and what it leaves for later.

Listen to this article · 7 min
Narration read by a synthetic voice from the text of this article.

Three stretches of seawall on Route 1A in North Hampton and Rye, about six-tenths of a mile in all, are what $20.3 million in federal highway money will rebuild. The Joint Legislative Fiscal Committee voted to accept the money on Nov. 20, 2026, without discussion, InDepthNH reported. The governor and Executive Council must approve it next.

The state’s own paperwork describes a much larger job. In the grant application the New Hampshire Department of Transportation prepared in August 2023, those three stretches are Phase 1 of a 14-section reconstruction. The application prices the phase at $25.3 million and lists $58.4 million more, in 2021 dollars, in work outside the grant.

Related coverage: GSR’s Nov. 20, 2026 report, New Hampshire Is Already Paying for Climate Change. Its Climate Plan Has No Number Anyone Must Meet., noted the committee’s vote in an account of the state’s climate plan; this piece covers the grant application behind the money.

What the grant buys

The application is titled New Hampshire Route 1A Revetment Reconstruction Phase 1. It asked the federal PROTECT program, a grant program dedicated to making transportation infrastructure more resilient, for $20,258,400. That is 80 percent of a Phase 1 budget of $25,323,000. The other $5,064,600 is the state’s match.

Phase 1 is three numbered sections. Section 7 runs from Philbrick’s Beach to just north of Rye Ledge and is budgeted at $6,331,000. Section 10, at Bass Beach, is $11,254,000. Section 13, from south of Fox Hill Point to north of Little Boars Head, is $7,738,000. The department called them “the highest priority revetments based on vulnerability to coastal storms.”

The $20.3 million the Fiscal Committee accepted matches that request. It also matches the $20,258,400 award that U.S. Sens. Jeanne Shaheen and Maggie Hassan and U.S. Rep. Chris Pappas announced on April 8, 2024.

What it leaves

The whole project, as the application describes it, is five wall sections and nine stone revetment sections along about 3.2 miles of Route 1A, built under five construction contracts over five years. One table sets out the budget beyond the grant, in 2021 dollars: $6.5 million for Section 1, $3.5 million for Section 2, $11.5 million for Section 3, $4.5 million for Section 4, $9.5 million for Section 5 and $18.5 million for Section 6, plus $500,000 for Sections 8, 9, 11, 12 and 14 together. With $3,725,000 for design and permitting and $126,390 for a completed study, it totals $58,351,390.

Another table sets the nine revetment sections side by side. In 2021 dollars, construction alone comes to $72 million. Sections 7, 10 and 13 account for $18 million of that, by GSR’s addition. Adjusted for inflation to 2026, the application’s total is $86.4 million.

Horizontal bar chart of 2021 conceptual construction cost estimates for nine Route 1A revetment sections, from the New Hampshire Department of Transportation’s August 2023 grant application. Phase 1 sections, covered by the grant: Section 7, 4.5 million dollars; Section 10, 8.0 million; Section 13, 5.5 million. Other sections: Section 1, 6.5 million; Section 2, 3.5 million; Section 3, 11.5 million; Section 4, 4.5 million; Section 5, 9.5 million; Section 6, 18.5 million. Total 72 million.
Construction cost estimates for the nine revetment sections, in 2021 dollars. Blue bars are the three Phase 1 sections the grant covers. The estimates cover the contractor’s work only; the five wall sections are not in this table. Chart: Granite State Report. Data: N.H. Department of Transportation, FY 2023 PROTECT grant application, Table 6.

Those construction figures leave out engineering, permitting and construction administration, and an appendix cautions that actual costs could run well above or below the estimates.

Two documents measure the wall differently. Transportation Commissioner David Rodrigue’s letter to the committee, as InDepthNH described it, counts 3.6 miles of state-owned seawall along an eight-mile stretch of the road. The 2023 application put the project at about 3.2 miles.

Why these three first

The application gives its reasons: the three sections sit close to the shore, have a history of cleanup expenses and are important to the local community. An appendix puts Route 1A’s cumulative closure time from 2011 through 2021 at 165 hours and 13 minutes, which the narrative describes as about seven full days. The walls and revetments were damaged in a series of nor’easters in March 2018.

The shoreline protection either existed before the storm of Feb. 6 and 7, 1978 or was built as emergency relief work after it, the application says. The new design is based on a 100-year flood plus two feet of sea level rise, with a 2050 horizon.

The calendar

The application said construction could begin in the fall of 2025. The award came in April 2024. Federal Highway Administrator Shailen Bhatt announced it at Rye Harbor State Park on April 22, 2024, the Associated Press reported. The Fiscal Committee’s vote to accept the money came on Nov. 20, 2026, at its last meeting of the legislative term.

A project page on the Town of North Hampton’s website describes what the Little Boar’s Head district should expect: work in the off-peak months of October through April, one-lane alternating traffic during portions of construction, and a potential temporary closure of part of Causeway Road during the Section 10 work. The page lists the timing as fall 2026, to be determined, and says the walls will keep the existing roadway alignment and a crest elevation consistent with the 1978 footprint.

On money for later phases, the application says the department is receiving an estimated $30,299,891 from a separate PROTECT formula program over five years, and that formula funds are among the money already allocated to design and permitting. GSR found no statement in it committing the formula money to building the remaining sections.

Next is the governor and Executive Council. Beyond that vote, the application’s own tables frame what is left: 11 more sections, priced in 2021 at $58.4 million.

Your Turn

Poll: What should come first for the rest of Route 1A’s seawall?
A) Rebuild all 14 sections as designed  ·  B) Rebuild only the sections that close the road most  ·  C) Study raising or moving the road  ·  D) Not sure

Discuss: Who should pay for the other 11 sections: the state, the federal government, the towns, or a mix?

Discuss: Is a 2050 horizon the right planning window for a coastal road?

You tell us: Live or work along Route 1A? Tell us what a closure costs you. Comment below or write to granitestatereport@gmail.com.

Fact check

#ClaimStatusSource
1The Joint Legislative Fiscal Committee approved, without discussion, accepting $20.3 million in Federal Highway Administration funds for Route 1A seawall work between North Hampton and Rye; three segments totaling about 0.6 miles; Governor and Executive Council approval is also needed; it was the committee’s last meeting of the term.ATTRIBUTEDInDepthNH, Garry Rayno, Nov. 17 and Nov. 20, 2026, citing Commissioner David Rodrigue’s letter to the committee. The Nov. 17 report set the meeting for that Friday; the Nov. 20 report describes the vote
2The application requested $20,258,400 against a Phase 1 total of $25,323,000, with a $5,064,600 state match.VERIFIEDN.H. Department of Transportation, FY 2023 PROTECT grant application narrative, Aug. 15, 2023, Table 2 (copy posted by the Rye Civic League); the 80 percent share recomputed by GSR in code
3Phase 1 is Sections 7, 10 and 13, budgeted at $6,331,000, $11,254,000 and $7,738,000, at the locations described; the “highest priority” description.VERIFIEDNHDOT grant application narrative, Table 2 and Section 2
4U.S. Sens. Shaheen and Hassan and U.S. Rep. Pappas announced $20,258,400 in PROTECT funding for Route 1A between North Hampton and Rye on April 8, 2024.VERIFIEDOffice of U.S. Sen. Maggie Hassan, press release, April 8, 2024
5The overall project is five wall sections and nine stone revetment sections along about 3.2 miles, under five construction contracts over five years.VERIFIEDNHDOT grant application narrative
6The budget beyond the grant lists the section figures given, plus $3,725,000 for design and permitting and $126,390 for a completed study, totaling $58,351,390 in 2021 dollars.VERIFIEDNHDOT grant application narrative, Table 3, “NH Rt 1A Project Budget Beyond Grant Scope”
7Construction of the nine revetment sections is estimated at $72 million in 2021 dollars and $86.4 million adjusted to 2026; the estimates cover the contractor’s work only; actual costs may vary.VERIFIEDNHDOT grant application narrative, Table 6 and Appendix G
8Sections 7, 10 and 13 account for $18 million of the $72 million.ATTRIBUTEDGSR arithmetic, recomputed in code, on Table 6 ($4.5 million, $8.0 million and $5.5 million)
9Commissioner Rodrigue’s letter counts 3.6 miles of state-owned seawall along an eight-mile segment of Route 1A.ATTRIBUTEDInDepthNH, Nov. 17 and Nov. 20, 2026
10The three sections were ranked highest for proximity to the shore, history of cleanup expenses and importance to the local community; Route 1A’s cumulative closure time for 2011 through 2021 is given as 165 hours and 13 minutes, about seven full days; damage came in nor’easters in March 2018.VERIFIEDNHDOT grant application narrative, Sections 3.2 and 5.3 and Appendix E. The appendix prints the 165:13 total; its listed rows include some closures on other roads
11The shoreline protection predates or followed the Feb. 6 and 7, 1978 storm; the design is based on a 100-year flood plus two feet of sea level rise with a 2050 horizon; construction could begin in the fall of 2025.VERIFIEDNHDOT grant application narrative, Sections 1.2 and 3.3
12Federal Highway Administrator Shailen Bhatt announced the grant at Rye Harbor State Park on April 22, 2024.ATTRIBUTEDAssociated Press, published by NHPR, April 22, 2024; the event date is confirmed in an NHDOT news release
13Work is anticipated in the off-peak months of October through April with one-lane alternating traffic during portions of construction and a potential temporary closure of part of Causeway Road during Section 10 work; timing is listed as fall 2026, to be determined; existing roadway alignment and crest elevation consistent with the 1978 footprint.VERIFIEDTown of North Hampton website, “NHDOT Route 1A Coastal Revetment Improvements”
14The department is receiving an estimated $30,299,891 from the PROTECT formula program over five years; formula funds are among those allocated to design and permitting; GSR found no statement in the application committing the formula money to building the remaining sections.VERIFIEDNHDOT grant application narrative, Sections 2 and 5.2; the absence is GSR’s reading of the full document
Have a document, a tip, or a correction?
Reach Granite State Report. Confidentiality respected where possible.
granitestatereport@gmail.com · 603-931-9264

Editor’s note. The cost, scope and closure figures above come from the New Hampshire Department of Transportation’s August 2023 PROTECT grant application, read in a copy posted by the Rye Civic League. The Fiscal Committee’s vote and Commissioner Rodrigue’s letter are attributed to InDepthNH. The award announcement is from the office of U.S. Sen. Maggie Hassan; the Rye Harbor event is from the Associated Press and an NHDOT news release. The application’s tables were prepared on different bases: its Phase 1 budget is a 2023 figure, and its other estimates are in 2021 dollars. The $18 million figure for Sections 7, 10 and 13 is GSR’s addition from the application’s Table 6. Corrections: Granite State Report corrects verified errors promptly and appends a note identifying what changed and when.

Granite State Report · Northfield, New Hampshire · granitestatereport.com
Board